CLIENT: UNIVERSITY OF TASMANIA
SECTOR: EDUCATION FACILITIES
SIZE: ALTERATIONS TO 5 HERITAGE BUILDINGS
PERIOD: 9 WEEKS
The UTAS Stage 1 project at Callum Park, located in Sydney’s inner west, is a heritage-listed site. The project was carried out on a live site, with the schedule coordinated around buildings still in use by students and faculty.
Stage 1 was completed in four phases, covering all internal fit-out refurbishments. The project also involved upgrading all service trades to meet current regulations and Australian standards. Throughout the project, care was taken to preserve the building’s heritage.
“CIP site management was very efficient, the program was managed well, and they co-operatively staged the works to avoid disruptions to the staff and students on site. “
TERRY LOCKWOOD
CLIENT PROJECT MANAGER – UTAS