CLIENT: TRANSPORT FOR NSW
SECTOR: GOVERNMENT
SIZE: 1,750 SQ.M
PERIOD: 9 WEEKS
This project was completed in two stages, both of which were expedited due to leasing issues.
The timeline was revised post-award to finish 2-3 weeks ahead of schedule for each stage. Each stage involved extensive work, including feature ceilings, pinnable wall fabrics, magnetic whiteboards, custom-made lockers, and feature carpet and vinyl throughout. The project also included a fully functional breakout area with stone benchtops, an accessible bathroom, joinery items, workstations, and loose furniture. Additionally, all service trades; fire, mechanical, hydraulics, electrical, and data—were upgraded or modified to suit the new office environment.
“SUPERIOR for all components of work. GOOD for project management documentation.”
ARIANE HYNARD
PROJECT MANAGER & CLIENT REPRESENTATIVE